Railway flyover „Hürlistein“
Principal surveys during construction
At the “Hürlistein” railway intersection near Kloten/Switzerland, the two-track lines from Wallisellen and Zürich Airport merge into a three-track line towards Effretikon. The level crossing of the tracks leads to conflicts in route scheduling and thus to a capacity bottleneck. The construction of a new, 400 m long flyover allows trains from Wallisellen to cross the Airport tracks without conflict. On both sides of the central bridge element, a 500 m long and a 1500 m long ramp are constructed respectively.
Our services
- Fixed point monumentation and measurement
- Survey of the topographic base data for project planning
- Set-out of the major construction elements: flyover, catenaries, signals and switches
- Building and track monitoring
- As-built documentation and control
- Data collection and processing for integrating the as-built documentation into the Swiss Federal Railway’s asset management GIS